University of Hull - Student Central

Client: University of Hull
Contract: Student Central, 3rd Floor Student Union Building Reconfiguration

We tendered for this project as part of Yorbuild 2 Lot 1, winning the tender on both price and quality. We negotiated a number of project changes which meant we had to make a quick start on site, the negotiating taking up a lot of the mobilisation time.

The project started on site quickly as it had to be finished ready for the new term for staff to move in. Another curved ball was handed to us when we were informed that some of the areas had to be completed and handed over within 2 to 3 weeks.

Our team hit the ground running and a number of resources were allocated to the project to make sure the Client’s requirements were met, and along with a large number of changes the project was completed ahead of programme.

Project Gallery

  • University of Hull - Student Central
  • University of Hull - Student Central
  • University of Hull - Student Central
  • University of Hull - Student Central
  • University of Hull - Student Central
  • University of Hull - Student Central
  • University of Hull - Student Central